Casino Christian School – Casino, School Electrical Expansions

Project

Casino Christian School - Casino, School Electrical Expansions, 2023

Scope of Works

  • Detailed assessment of existing aged Switchboard systems and generation of a Site Master Single Line Diagram
  • Design, Construction, Installation & Commissioning of a new 400A Main Switchboard with automated Controls
  • Design, Construction, Installation & Commissioning of a 3 x new 250A Main Distribution Boards
  • Training of Operators
  • Submission of accurate As-Built CAD Drawings upon completion
  • Certification to the Customer and Supply Authority

 

Adventist Senior Living – Alstonville, Back-up Power Generation for Site

Project

Adventist Senior Living - Alstonville, Back-up Power Generation for Site, 2023

Scope of Works

  • Detailed assessment of existing aged Switchboard systems and generation of a cutover plan to integrate Back-up Power for Site
  • Design, Construction, Installation & Commissioning of a new 250A Diesel Generator
  • Design, Construction, Installation & Commissioning of an Automatic Transfer Switch into the Main Switch Room
  • Training of Operators
  • Submission of accurate As-Built CAD Drawings upon completion
  • Certification to the Customer and Supply Authority

NSW Dept of Health – Lismore Hospital Linen Service Laundry

Project

NSW Dept of Health - Lismore Hospital Linen Service Laundry 2024

Scope of Works

  • Detailed assessment of existing aged Laundry Control systems and generation of a cutover plan to modernise Site
  • Design, Construction, Installation & Commissioning of a new 630A Main Switchboard with Lightning Protection and Electronic Sub-metering
  • Design, Construction, Installation & Commissioning of a 3 x 250A Main Distribution Boards
  • Re-pair of the existing overhead Cable-Tray Systems and modifications to the Floor-pit coverage with custom-Aluminium panelling
  • Training of Operators
  • Submission of accurate As-Built CAD Drawings upon completion
  • Certification to the Customer and Supply Authority

Ballina Shire Council – Waste Water Treatment Plant

Project

Ballina Shire Council - Waste Water Treatment Plant 2021

Scope of Works

  • Detailed assessment of existing aged Pump Control systems and generation of a cutover plan to modernise Site
  • Design, Construction, Installation & Commissioning of a new 630A Motor Control Centre with PLC control and 110KW VSD's
  • Training of Operators
  • Submission of accurate As-Built CAD Drawings upon completion